Topics getting the most attention in Lima public meetings, ranked by how frequently they come up.

7 issues (filtered)12 topics
MediumWater Utilities

Brightspeed broadband service failures

A returning resident described a 1.3-star internet provider whose technicians never show and whose billing hurts elderly customers — and asked council to pursue accountability or oversight.

1 mention (1 this month)Last discussed Oct 26, 2026
HighWater Utilities

Cable Road sanitary sewer force main replacement

Councilor Wilkerson questioned spending $35,400 on engineering before the November Cable Road vote; Utilities Director Caprella said the forcemain has leaked 11-12 times in five months and must be replaced no matter what.

4 mentions (1 this month)Last discussed Oct 12, 2026
LowWater Utilities

Golf at Sugar Creek water agreement termination

The city planned to formally end a 2004 water service agreement with Golf at Sugar Creek, which would then just be treated like any other water customer under standard rates and policies.

1 mentionLast discussed Sep 14, 2026
HighWater Utilities

Rumpke trash service performance

Residents near Republic Garbage's dumpsters have dealt with rats for years because the dumpsters aren't cleaned out. Council referred the issue to the Neighborhood Concerns Committee and asked that the company's manager be contacted.

2 mentionsLast discussed Sep 14, 2026
MediumWater Utilities

Resident sewage backup and flood damage claims

A resident described a sewage backup during street work that ruined belongings and said no one from the city or his councilman followed up. Councilman Neeper said calls were returned and heavy rain caused flooding.

2 mentionsLast discussed Sep 14, 2026
MediumWater Utilities

Stormwater assessment updates

Property owners whose stormwater assessments changed after the 2026 citywide review are getting notices — some up, some down — with instructions for requesting a re-review.

3 mentionsLast discussed Jul 13, 2026
MediumWater Utilities

Wastewater emergency repair

A $231,000 emergency purchase of a return activated sludge pump and valves kept the wastewater treatment plant running.

1 mentionLast discussed Jun 22, 2026