A $1.28 million contract with The Shelly Company would resurface about 6.18 miles of city streets, funded by a mix of state grants and local funds. Work was planned for summer through November 2026.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 22, 2026.

Impact analysis

💰Financial impact

Costs $1,276,036.80, mostly offset by OPWC and CDBG grants.

✅Who benefits

Drivers and residents on the resurfaced streets get smoother, safer roads.